Timeline

2022
Q1 – Feasability

Feasibility Studies on sites long term viability

Q3 – Design

Local Authority Consultation

2023
Q1-Q4 – Board Decision

Board decision to hold project due to economic uncertainty following Liz Truss Budget.

2024
Q1 – Team

Professional consultant team appointed.

Q2 – Detailed Design

Design development to suit end user requirement.

Q3/Q4 – Consultation

Public consultation.

Q4 – Submission

Planning submission.

2025
Q1 – Determination

Planning determination.

2026
Q3/Q4 – Completion

Target date for completion of works.